
Project implemented
Non-return valve and water-meter installation in Jásztelek
Two ball-back valves on high-five. Y-was fitted with a water clock and connected with the Alabama Szer Kft. The Jászberényi KOSSUTH Zrt. of.
- Year completed
- 2026
- Site
- Jásztelek, Zagyva ártér
- Work completed
- Pipework systems
We built two-ball return valves and water meters in Jastelek, in the Zagyva Barn, and Y-We've created a connection. M Jászberényi KOSSUTH Zrt. for pipework systems work on the Alabama Szer Kft. completed in February 2026.
pipework systems installation in Zagyva's price area
Our work in Jástelek included the construction of fittings and measuring points related to the existing pipeline. M Jászberényi KOSSUTH Zrt. the installation of two ball return valves on its behalf, Y-connection design and watermeter installation. Size designation of the part of work undertaken DN 300–DN It was 250.
The implementation of Alabama Szer Kft. completed as a pipework system task agreed with the customer. The work on the ground took place in the Zagyvaselt area of Jasztek, next to the wire found. The installation is therefore directly connected to the existing system.
Reflector valves, Y-connection and hydrometer
It is for the return valves to ensure the required flow direction on the line and to prevent the flow of the medium. Two ball-back valves were installed in the manger shed. These are pipework systems assemblies linked to the direction of flow in the wire.
Part of the task was Y-This appropriation is intended to cover expenditure relating to officials and temporary staff working in the field of external personnel and other staff working in the field of external personnel. This gives the connection point of the wires, adapted to the location pipework systems. The installation of the water meter allows for measuring the flow of water. The fittings and the measuring point together formed the work part of the construction part of the mandate.
On-site work and finished work
On-site installation took place from 9 to 11 February 2026, over three working days. Access to the installation points and completion of the agreed connections were required alongside the exposed pipeline. Pipe assembly in the excavation was adapted to the existing pipeline’s position and the available access.
The two-ball return valve and the water meter have been installed, and Y-connection. M Jászberényi KOSSUTH Zrt. we have completed the pipework systems installation task undertaken by the company. The Jástelek reference is an example of our work on on-site installation and installation of piping and fittings related to the existing pipeline network.
Alabama Szer Kft.














